Al Maktoum Airport Contracts: What Dubai’s New AED56.5bn Awards Will Build

Dubai has awarded new Al Maktoum International Airport contracts worth about AED56.5 billion, taking the total awarded to date to about AED80 billion. Here is what the four packages will build.

Arman Babagoli
Arman Babagoli
November 26, 2026 β€’ 11 views β€’ 0 likes
Al Maktoum Airport Contracts: What Dubai’s New AED56.5bn Awards Will Build
Rendering of the future passenger terminal at Al Maktoum International Airport in Dubai. Official rendering; file image, not from the 26 November 2026 announcement. Photo: Dubai Media Office.

Al Maktoum airport contracts worth approximately AED56.5 billion were announced on Thursday 26 November 2026 by H.H. Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, Deputy Prime Minister, Minister of Defence and Chairman of The Executive Council of Dubai. According to WAM, the new awards bring the total value of contracts and packages awarded to date for Al Maktoum International Airport to about AED80 billion.

The contracts were awarded under the directives of H.H. Sheikh Mohammed bin Rashid Al Maktoum, Vice President, Prime Minister and Ruler of Dubai. They cover substructure works for the West Terminal, Concourse 1 and Concourse 4, the above-ground buildings and roofs of Concourses 2 and 3, and two main power substations. H.H. Sheikh Ahmed bin Saeed Al Maktoum, Chairman of the Dubai Aviation City Corporation and Chairman of Dubai Aviation Engineering Projects, said the project “has entered a phase of large-scale construction”.

Below is what the new packages will build, how the totals add up, what has been done on site so far and what the announcement means for Dubai residents and for Dubai International (DXB).

Al Maktoum airport contracts: how the totals add up

The figure to keep in mind is that AED80 billion is the value of contracts awarded so far. It is not the cost of the whole project. In the preceding phase, Dubai Aviation Engineering Projects (DAEP) awarded contracts and packages worth approximately AED23.815 billion. Adding today’s AED56.5 billion gives the official total of about AED80 billion, as set out by WAM and the Dubai Media Office.

Contracts and costValue
Earlier contracts and packagesApproximately AED23.815 billion: enabling works, substructure packages, and the Automated People Mover and Baggage Handling systems contracts
New contracts, 26 November 2026Approximately AED56.5 billion
Total awarded to dateApproximately AED80 billion
Approved cost of the new passenger terminal (April 2024)AED128 billion

The AED128 billion figure dates from 28 April 2024, when Sheikh Mohammed approved the designs for the new passenger terminal and the start of construction, WAM reported at the time. It is a separate number from the value of contracts awarded so far.

Advertisement

Google Display Ads

728x250

In his post on X on Thursday morning, Sheikh Hamdan wrote: “Under the directives of His Highness Sheikh Mohammed bin Rashid Al Maktoum, today we announce the award of new contracts worth AED 56.5 billion for the development of Al Maktoum International Airport, bringing the total value of contracts awarded for this strategic project to more than AED 80 billion.”

What the new Al Maktoum airport contracts will build

The official statement groups the new awards into four areas of Phase One. It does not name the contractors or give a value for each package.

PackageWhat it covers
West Terminal Building and Concourse 1: substructureBasements, underground tunnels, access ramps, short-term car parks and the Ground Transportation Centre, plus metro interface works and landside bridges. Also underground ground service equipment (GSE) corridors, the main baggage handling backbone network, and power, water, telecoms, sewerage and stormwater networks. This is the below-ground base for the terminal buildings that will follow.
Concourses 2 and 3: superstructure and building systemsThe main above-ground concourse buildings, rotundas, structural steel bridges and supports for passenger boarding bridges, large-span steel roof spaceframes, faΓ§ades, roofing, architectural fit-out, mechanical, electrical and plumbing (MEP) installations and Special Airport Systems.
Concourse 4: substructureBasements, underground tunnels, access ramps, GSE corridors, utility networks and underground parts of the baggage handling backbone, ready for later stages of the concourse.
Electrical power infrastructureTwo principal 132/11 kV substations, power cabling and related electrical works, covering construction, installation, testing, commissioning and handover.

According to WAM, these awards “enable construction to advance concurrently across several key components of Phase One”. The Concourse 2 and 3 packages build on substructure contracts awarded earlier for the same two concourses. The Automated People Mover and the Baggage Handling systems contracts are not part of today’s awards. They were included in the earlier AED23.815 billion.

Progress on site so far

DAEP said enabling works in the Concourse 2 and Concourse 3 zones and in the central area of the site are nearing completion. These areas include the baggage handling tunnels, GSE routes and the main baggage handling network. Enabling works are still going on in the central passenger terminal zone, which covers the West Terminal, Concourse 1 and the Ground Transportation Centre, and in the Concourse 4 area.

The official figures to date are:

Advertisement

Google Display Ads

728x250

  • More than 24.23 million cubic metres excavated
  • More than 5.2 million cubic metres of backfilling
  • 7,635 piles completed
  • More than 875,603 cubic metres of concrete and over 226,270 tonnes of reinforcement steel in the Concourse 2 and 3 substructure packages
  • About 14,000 workers across these packages, with more than 21.3 million working hours
An architectural rendering of a vast white airport terminal hall with curved roof supports, circular landscaped islands of grass and palm trees, walkways and small figures of travellers.
Rendering of the interior of the future passenger terminal at Al Maktoum International Airport in Dubai, with planted courtyards beneath a sweeping white roof. Official rendering from the April 2024 design announcement. Photo: Dubai Media Office.

When will Al Maktoum International Airport open?

Thursday’s statement did not give an opening year. Sheikh Ahmed bin Saeed said: “We are moving decisively ahead with Phase One in accordance with the approved programme. The contracts and delivery sequence have been structured to sustain parallel progress across multiple sites while upholding the highest standards of quality and safety.”

The most recent official date came on 15 June 2026, when WAM and the Dubai Media Office said work was proceeding in line with approved timelines and that the project “remains on course to commence operations in 2032, in accordance with its long-term master plan.” That date is for the start of operations with Phase One, not for the completion of the whole airport. When the terminal designs were approved in April 2024, Sheikh Ahmed said the first phase was expected to be ready within 10 years, with a capacity of 150 million passengers a year.

Al Maktoum International Airport in numbers

When fully completedOfficial figure
Passenger capacityMore than 260 million passengers a year (Sheikh Hamdan, 26 November 2026)
Air cargo12 million tonnes a year (June 2026 statement)
RunwaysFive parallel runways (June 2026 statement)
Terminals and concoursesTwo passenger terminals and seven concourses (June 2026 statement)
Aircraft standsMore than 430 (June 2026 statement)
Site area70 square kilometres (April 2024 master plan)

The 260 million figure applies to the airport once every phase is complete, not to Phase One. Sheikh Hamdan wrote: “Once fully completed, Al Maktoum International Airport will have the capacity to handle more than 260 million passengers annually”, and described the project in his post as “the world’s largest and best airport”.

What it means for Dubai residents and DXB

The long-term plan is for Dubai International to hand over to the new airport. In April 2024, Sheikh Mohammed said Al Maktoum International “will be five times the size of the current Dubai International Airport, and all operations at Dubai International Airport will be transferred to it in the coming years.” In June 2026, Khalifa Al Zaffin, Executive Chairman of Dubai Aviation City Corporation, said work was under way to ensure “a smooth and carefully managed transition of operations from Dubai International Airport to the new airport”. No date for that move has been announced, and DXB remains Dubai’s main passenger airport.

DXB is also still being upgraded. The June 2026 statement described a separate programme for existing airport infrastructure at DXB and at the current Dubai World Central terminal, with a budget of AED16 billion and more than AED7.5 billion in contracts already awarded. That budget is not part of the AED80 billion awarded for the new airport.

Advertisement

Google Display Ads

728x250

For getting to the airport, the West Terminal packages awarded on Thursday include metro interface works, landside bridges, short-term car parks and a Ground Transportation Centre. These are the structures that will link the terminal to the wider transport network.

The airport sits in Dubai South. When the designs were approved in April 2024, Sheikh Mohammed said that “as we build an entire city around the airport in Dubai South, demand for housing for a million people will follow.” Our analysis of Al Maktoum Airport real estate and the Dubai South outlook looks at which areas could benefit and what sales data shows so far. Companies weighing a base near the airport can compare the options in our guide to Dubai mainland vs free zone company setup.

Sheikh Ahmed said that once operational, the airport “will provide Dubai with the capacity needed to support the continued growth of its national airlines and meet rising passenger and cargo demand over the coming decades.” Sheikh Hamdan linked the project to the Dubai Economic Agenda, D33, which aims to double the size of Dubai’s economy. For the wider picture, see our features on the UAE aviation industry and Dubai as a global transit hub.

Who is delivering the project?

Dubai Aviation Engineering Projects has overall responsibility for delivering the Al Maktoum International Airport programme, from planning and design through procurement and construction to operational readiness. It sets the order of contract packages, manages technical interfaces and monitors quality, safety, cost and schedule with government entities and delivery partners. The full official statement is on WAM. For more news on Dubai’s economy, follow our Business section.

Rate this article

Your feedback helps other readers and improves our recommendations.

Average rating

0.0 /5

0 ratings

Select a star to submit your rating.

Enjoyed this article?

Share it with your network

About the Author

Arman Babagoli

Arman Babagoli

Arman Babagoli is the CEO of DubaiPress, where he leads editorial strategy and growth, and writes on business news, entrepreneurship and investment. A lawyer with many years of legal experience, he brings a legal perspective to business stories and helps readers in the UAE understand the legal side of doing business. His articles provide general information. For a specific case, readers should consult a licensed lawyer.

πŸ‘€ View all articles
πŸ’¬

Comments (0)

Leave a Comment

No comments yet. Be the first to share your thoughts!